OkPowell Williams as the client’s Project Manager, has certified Practical Completion of the extensive refurbishment of the Quadrant 2 office block at Siemens’ Ruston Works Lincoln site, where they manufacture gas turbines. This is the third large project Powell Williams has been involved in on the site over last 7 years.
The extent of the project
As Project Manager, we were involved from the feasibility stage through to completion.
The original scheme involved demolition to parts of the building along with significant refurbishment of the three floors of the office accommodation in order to accommodate Siemen’s staff relocating from other sites.
The project had to be significantly value engineered to meet the client’s financial requirements, which involved detailed and careful consideration of the design, to ensure the new office environment would meet the client’s operational needs.
Simon Cann of Siemens Energy said:
“Paul has worked with Siemens for a number of years. He understands our systems, our operational needs and always offers simple, pragmatic advice. We continue to work with Paul as he adds value and we are delighted with the outcome of this project.”